Said the Sabah Pan Borneo Highway cost rose from RM12.86 billion to RM24.89 billion after the project switched from the project delivery partner model to conventional federal contracts in 2019.
The Works Ministry said Sabah Phase 1A stood at 85.25 per cent against a scheduled 93.96 per cent as of October 2025 and told contractors to work overtime. Source: Malay Mail